Tend & Keep Off-Grid Systems · Lesson 6 of 8 · Putting it together Course home
Off-Grid Systems · Lesson 6 of 8

Putting it together

The site plan, the build order and the inspections
About 30 min to read5 partsSample site planHands-on practice

You now know the rules, water, waste, power and storage on their own. This lesson puts them on one piece of land, in one order, so that each system helps the next instead of getting in its way.

Most expensive homestead mistakes aren't bad systems. They're good systems in the wrong place or the wrong order: a leach field where the well needed to go, solar shaded by the barn, a trench dug twice, a permit that expired while you waited on materials. Planning the whole site first prevents nearly all of them.

By the end of this lesson you will be able to
  1. 1Draw a site plan that places every system where it works best.
  2. 2Lay out the seven stages of an off-grid build in the right order.
  3. 3Know which inspections come when, and how to pass them the first time.
  4. 4Keep your permit alive from start to finish.
  5. 5Build wildfire safety into the plan from the start.
Part 1

The site plan: one drawing, every system

A site plan is a bird's-eye drawing of your land showing every building and system. Your county will ask for one, but its real value is for you: it's where conflicts show up on paper instead of in the dirt.

One sample site plan, every system in its place. downhill County road Driveway (fire access) 100 ft · reduce fuel 30 ft · lean and green Home W Well keep septic & animals out of 100 ft Water tanks uphill · gravity to garden Kitchen garden Greenhouse Ground-mount solar Power shed Septic tank Leach field · wildflower meadow Reserve area Orchard · laundry greywater Not to scale. Your county sets the real setbacks; draw yours to scale in the practice below.

The placement rules that matter most

  1. Water first and highest. Put the well uphill of septic and animals, with at least 100 ft between the well and any septic system. Tanks go uphill of the garden so gravity does the work.
  2. Waste downhill, with a spare. The septic tank and leach field go downhill of the well, and many counties want a reserve area for a future replacement field. Keep both free of driveways and buildings.
  3. Sun gets the clearest ground. Put the solar array where winter shadows don't reach (Lesson 4), close to a cool, protected power shed.
  4. The house sits in the middle of it all. Short pipe and wire runs save money and power. Consider views, morning light into the kitchen, and the walk to the garden.
  5. Fire trucks must get in. The driveway needs to be wide and firm enough for emergency vehicles, with room to turn around.
The design opportunity

When systems are placed well, the land composes itself. The tank on the rise above the garden, the meadow over the leach field, the orchard drinking laundry water, panels glinting beyond the house: function and beauty end up in the same places.

Part 2

The build sequence

Each stage depends on the one before it. Skipping ahead is the most common way to pay for something twice.

Seven stages, in the order that avoids costly redos.1Buy rightSoil test, water, access and zoning checked before closingLesson 12Prove waterDrill and test the well; it's often needed for the permitLesson 23Design & permitSite plan, house plans, septic, well, solar and fire reviewLessons 1–54GroundworkDriveway, trenches, foundation, septic tank and leach fieldInspections5Build the shellFraming, roof, windows, then rough plumbing and electricalInspections6Systems onSolar, batteries, pump, water treatment, greywaterInspections7Finish & finalInsulation, interiors, defensible space, final sign-offMove in
Stages 1 and 2 happen before you commit to building. They decide whether the rest is possible.

Why water comes before design

In many counties you must show a working, tested water supply before a building permit is issued (Lesson 2). Drilling the well early also tells you how deep and how productive it is, which shapes the pump, the power system and the budget. And construction itself needs water.

Power during construction

There's no grid to plug the saw into. Plan temporary power from day one: a generator, a portable solar trailer, or installing the permanent ground-mount array and power shed early so the build runs on the sun.

Part 3

Inspections, in order

Inspections follow the build. Each one has to pass before you cover up the work it checks, so a missed inspection can mean tearing out finished work. Your county gives you its own list; this is a typical order.

StageTypical inspectionWhat they check
Before pouringSetbacks and foundationLocation on the site, footing size, steel, forms
Before backfillingUndergroundWater lines, drain lines and electrical conduit in open trenches
SepticTank and leach fieldTank placement, field layout and depth, before it's covered
Shell upFraming and rough-inStructure, plus rough plumbing, electrical and mechanical before walls close
Walls openInsulation and energyInsulation as specified on your energy compliance forms
SystemsSolar, batteries, generatorEquipment, wiring, disconnects, labels, battery location
The endFinalEverything complete, safe and matching the plans, plus fire department sign-off where required

Pass the first time

  1. Keep the approved plans on site. The inspector checks your work against them. Changes need approval first.
  2. Call before you cover. Never pour, backfill or close a wall until that inspection is signed.
  3. Walk it yourself first. Use the county's checklist the day before. Most failed inspections are small, fixable things.
  4. Keep a binder. Signed cards, photos of open trenches and walls, and product manuals. It's your home's history, and future buyers and insurers will value it.
Part 4

Keeping your permit alive

In California, a building permit generally stays valid for 12 months after it's issued if work begins in that time. Once work starts, it can expire if the work is suspended or abandoned for 180 days in a row. Passing an inspection is the clearest proof of progress, and it resets the clock.

Plan your milestones
  • Schedule your first inspection soon after the permit is issued
  • Space inspections no more than about five months apart
  • Order long-lead items like windows and batteries early
  • Ask for an extension in writing before a deadline, not after
Check locally

Some building departments set shorter administrative deadlines, and extensions are granted for good cause such as weather or supply delays. Ask how your county handles it when you pick up the permit.

Part 5

Wildfire safety, built in

In much of rural California, wildfire shapes the whole plan. State law requires defensible space around homes in fire hazard areas, and new homes in those areas face fire-resistant building and access standards.

Zone 0 · 0–5 ft

Ember-resistant

Nothing that can catch a wind-blown ember: no bark mulch, firewood or combustible plants against the house.

State rules are still being finalized; insurers already ask about it.

Zone 1 · 0–30 ft

Lean, clean, green

Remove dead plants and debris, keep plants watered and spaced, and clear roofs and gutters.

Move woodpiles out to Zone 2.

Zone 2 · 30–100 ft

Reduce fuel

Mow grass to 4 inches or less, and space trees and shrubs so fire can't climb or jump.

Spacing increases on slopes.

The design opportunity

Defensible space and a beautiful homestead want the same things: an irrigated kitchen garden near the house, gravel paths, stone walls, a mowed orchard, and a meadow kept short. Fire-wise planting can be the most beautiful planting on the land.

Hands-on practice · two afternoons

Draw your master plan

Everything from this course comes together on one sheet. Your family will draw a site plan to scale, place every system using the rules you've learned, and lay out the build order as a timeline on the wall.

You'll need

  • Large graph paper (1 square = 5 ft) or Floorplanner
  • A compass and string to draw circles
  • Colored pencils
  • Sticky notes in two colors
  • Your worksheets from Lessons 1–5
  • Optional: a free aerial view of real land from a map app

Do it together

  1. Draw the land. Mark the road, the property lines, which way is north, and which way is downhill.
  2. Place the well uphill, and draw a 100 ft circle around it. Nothing septic goes inside.
  3. Place the septic and leach field downhill, plus a reserve area.
  4. Place the home using your footprint from Lesson 1, then the water tanks, garden, solar array and power shed.
  5. Draw the fire zones: rings at 5, 30 and 100 ft around the home.
  6. Build the timeline. Write each of the seven stages on a sticky note, add the inspections in another color, and put them in order on a wall.
AGES 5–8

Little planners

  • Color each system: blue for water, brown for waste, yellow for sun
  • Draw the garden and where the chickens go
  • Put the sticky notes in order with help
AGES 9–14

Older planners

  • Draw everything to scale and measure every setback
  • Find one conflict in the first draft and fix it
  • Estimate how long each stage might take and add dates

Keep this plan. You'll use it in the next two lessons to build your budget and walk a real site from start to finish.

Closing

A place where everything fits

A good plan feels inevitable once it's drawn: of course the tank sits above the garden, of course the meadow covers the leach field, of course the panels face the open sky. Getting there takes patience, an eraser, and a willingness to move things around on paper as many times as it takes. That patience is cheap. Moving things after they're built is not.

Next we put numbers to the plan: what each part costs, what to build first, and what can wait for year two.

Worksheet

Your Lesson 6 worksheet

Work through these together. Your answers save on this device as you type, and print cleanly for your records.

For your homeschool records

Progress record

What this lesson practices:

  • MathScale drawings, measuring distances, and circles of a given radius (Common Core 7.G.A.1, 7.G.B.4).
  • GeographyReading slope, orientation and land features; making and reading maps.
  • ScienceWildfire behavior and how people reduce natural hazards (NGSS 3-ESS3-1, MS-ESS3-2).
  • Life skillsSequencing a complex project, planning milestones, and keeping records.

Standards mapping is a draft. If you use charter or ESA funds, confirm it with your education specialist.

Sources for this lesson